Tumbler Ridge moves to replace its Upper Bench building freeze with case-by-case geotechnical permits

A housing plan council shelved a year ago is coming back, starting with a fix for homeowners who have not been allowed to build since 2023.

Published Nov 10, 2026 in Tumbler Ridge
By The NEBC Current newsroom
The red and white Tumbler Ridge town hall with its clock tower, in an older photo
Tumbler Ridge town hall, home of the District that set the Upper Bench freeze. Older file photo. Photo: Maclean25 via Wikimedia Commons, CC BY-SA 3.0

TUMBLER RIDGE, B.C. - Homeowners on part of Tumbler Ridge's Upper Bench who have been barred from building since 2023 could get a way forward, under draft rules put in front of council's policies and priorities committee on Monday.

Council passed a moratorium on April 6, 2023, that stopped new buildings, retaining walls and property expansions on certain lots along Gwillim Crescent, Murray Drive, Sukunka Place and Wapiti Crescent, near Highway 52 North. District records say engineering studies going back to the 1980s found drainage and ground-stability problems in that area.

The district now proposes a new development permit area to take the freeze's place. Under the draft, anyone planning a new house or accessory building, an addition that adds footprint or weight, a subdivision, a retaining wall, new subsurface drainage, or digging and filling deeper than 0.15 metres would need a permit first. The district could ask for a report from a professional engineer, proof the work will not make things worse for neighbours or town pipes, specific mitigation such as drainage or foundation design, and a covenant on title. Interior renovations, routine upkeep and light landscaping would not need one.

"The proposed DPA is not intended to prohibit development," the staff report says. Each lot would be judged on its own, because the risk changes from one property to the next, according to the draft.

Monday's report was for information only. The permit area needs an amendment to the Official Community Plan, which will come to council in a separate report with its own public process. After that, the residential development plan the moratorium sits inside can return for adoption. Council deferred that plan on Nov. 17, 2025, Tumbler RidgeLines reported at the time, so staff could work on the ground-stability question.

The plan, written by Urban Systems, lays out why the district wants homes built at all. Using provincial formulas, it estimates Tumbler Ridge needs about 395 new housing units by 2041. Most of the town's homes went up in the 1980s, when it was built almost overnight for the coal mines, and the plan notes that serviced lots sit empty while few new houses get built.

Cost is the wall. The typical assessed value of a single-family home rose from $180,000 in 2024 to $203,000 in 2025, according to BC Assessment figures in the plan. But building a new house in northern B.C. runs about $275 to $450 a square foot before land, permits and other costs. The plan works through one example and arrives at about $487,000 for a new home on a district lot, more than double the typical assessment. Nearly 87 per cent of people who answered the district's survey said they could spend no more than $300,000 on a home.

Land is not the problem, the plan suggests. The district has promoted its own lots for about a decade at prices from $10,000 to $730,100, but it recorded only two sales from 2014 to 2024, one commercial and one industrial.

Of three district-owned sites studied, the plan picks the Upper Bench, a 17-hectare stand of forest between Mackenzie Way and Highway 52, for future housing. Its concept begins with 10 lots off Wolverine Avenue, larger than the neighbours' lots, with duplexes, triplexes and multi-family housing in later phases. Servicing a new lot of about 0.1 hectares could top $295,000 at 2026 prices, the plan estimates, compared with about $85,000 for lots in Taylor's Jarvis subdivision built in 2020.

The committee meeting was also set to go behind closed doors to discuss land, under the section of the Community Charter that covers buying and selling property.

Sources: District of Tumbler Ridge, Policies and Priorities Committee agenda package (Nov. 9, 2026), including the staff report "Residential Development Plan: Background and Next Steps," the Urban Systems Residential Development Plan (November 2025) and draft Development Permit Area 7. Tumbler RidgeLines, "Council defers Residential Development Plan" (Nov. 28, 2025). District of Tumbler Ridge, Regular Meeting of Council agenda (Nov. 2, 2026)..