Local
Tumbler Ridge gas bills would drop and Dawson Creek's would tick up under PNG plan to merge Northeast rates
The utility says it would collect no more money overall, and the commission gets the final say.
By The NEBC Current newsroom
DAWSON CREEK, B.C. - Pacific Northern Gas wants every customer in its Northeast service area to pay the same delivery rate, and the change would trim Tumbler Ridge heating bills while adding a few dollars a year in Dawson Creek and Fort St. John.
The utility posted the proposal Monday, Nov. 9. Under the plan, the Fort St. John/Dawson Creek division and the Tumbler Ridge division would be merged, and the combined territory would go by the name PNG-East. Once the change is complete, customers in the same rate class would pay the same basic monthly charge and the same delivery charge whichever of the three communities they live in.
For a typical house, PNG estimates the shift would add about $3 a year in Fort St. John, a 0.2 per cent increase, and about $8 a year in Dawson Creek, or 0.7 per cent. Tumbler Ridge homeowners would save about $79 a year, a cut of roughly 6.8 per cent. Those amounts apply in each year of a three-year phase-in, so the old gaps close in steps. The company based them on its 2027 approved rates and average use, and actual bills will depend on how much gas a household burns.
Businesses see a wider spread. In Tumbler Ridge, small commercial accounts would save about 8.6 per cent a year and large commercial accounts about 9.2 per cent. Dawson Creek's small and large commercial customers would pay about 1.6 and 2.3 per cent more, while its small industrial customers would pay about 1.3 per cent less. Every Fort St. John class moves by less than half a per cent either way.
PNG is taking the plan to local councils before it files. Tumbler Ridge council is set to hear from the company's director of business development, David Keir, and its Indigenous and stakeholder relations lead, Joan Isac, at its regular meeting Monday, Nov. 16. Their slides use the town's civic centre as a worked example. At roughly 10,000 gigajoules a year, its delivery bill of about $80,590 would fall by about $7,300 a year once the change is fully in place.
The company says the plan changes how costs are divided among Northeast customers, not the total it is allowed to collect. The commodity charge, the price of the gas itself, has been common across PNG's service areas since 2024 and is passed through without markup. PNG argues that a bigger shared customer base means a large industrial customer opening, expanding or closing in one town would no longer land on that town alone.
PNG also points out that its Northeast customers already pay the lowest natural gas rates in B.C. It said it started looking at a change after encouragement from the B.C. Utilities Commission and from interveners in earlier rate hearings. Its western division, which runs from Vanderhoof to Prince Rupert, would keep separate rates, because the company says merging the two would push a bigger share of the West's higher costs onto Peace customers.
The company plans to send the application to the commission in December. Regulators would review it in early to mid-2027, and the public will be able to send letters of comment or apply to take part as interveners. If it is approved, the new structure would start Jan. 1, 2028, and phase in through 2030. Customers can send questions now through the company's project page at png.ca/CommonRates.
Sources: Pacific Northern Gas, "PNG Proposes Common Basic Charges and Delivery Rates for Northeast Customers" (Nov. 9, 2026). Pacific Northern Gas, Northeast and Common Rates project page (retrieved Nov. 13, 2026). District of Tumbler Ridge, Regular Meeting of Council agenda, item 6.2, PNG delegation and presentation (Nov. 16, 2026). B.C. Utilities Commission, order on Pacific Northern Gas (N.E.) Ltd. 2025 to 2027 revenue requirements for the Fort St. John/Dawson Creek and Tumbler Ridge divisions..
You may like
December is one of the most dangerous months on B.C. roads, and safety groups are urging drivers to slow down and plan ahead
Company behind a 30-turbine wind farm south of Fort St. John asks the regional district to rezone farmland, and directors push back
Twelve more First Nations buy into Coastal GasLink, the pipeline that starts near Dawson Creek
School District 60 cancels buses as freezing rain glazes Peace roads, but schools stay open