Northern Health sets March 21 as move day for the new Dawson Creek hospital
A health authority update headed to the regional hospital board puts a date on the switch, but says equipment testing is running behind.
By The NEBC Current newsroom
DAWSON CREEK, B.C. - Patients at Dawson Creek and District Hospital are expected to be moved into the new hospital on Sunday, March 21, 2027, according to a Northern Health update going to the Peace River Regional Hospital District board this week.
It is the first firm date to appear in public. Until now Northern Health's project pages and its spring update said only that the $590-million hospital would open sometime in early 2027, with a date to follow once planning wrapped up.
The update is dated Oct. 5 and sits in the agenda package for Thursday's hospital board meeting. It also shows the handover target moving again. In February the health authority announced that the builder, Graham Design-Builders, had pulled substantial completion ahead two months, from Nov. 30 to Sept. 29. The October slides give the target as Oct. 14.
Outside, the job is done. Northern Health reports the landscaping is finished, the lots are paved and lined, and more than 150 workers were still on site finishing the interior and installing equipment. The weak spot is commissioning. Testing of air balancing, door systems and life safety equipment is behind schedule, the update says, and that is squeezing the time staff have for training and orientation in the new building.
Health Care Relocations, the company hired to run the move, has set up its patient transfer committee and is finishing plans department by department. Northern Health has said it wants everything done in a single day, with patients moving in a steady stream from the old building to the new one. CBC News has reported the new hospital sits kitty-corner to the current one.
The new building is more than 50 per cent larger than the hospital it replaces. Northern Health lists 70 beds, 24 more than now, all in single rooms with their own washrooms. The emergency department doubles in size and goes from 10 treatment spaces to 15. Mental health beds rise from 15 to 18.
The 1960 building it replaces has a facility condition index of 0.84 in the same package, with about $106 million in repairs and renewals listed against a replacement value of about $127 million. Northern Health plans to take it down once the new hospital is running.
The new hospital will also carry Cree and Dane-zaa companion names, which the Northern Health board approved in July, the update says. They are given as Natawiho and Yuu dane kwǫ, which the document translates as Healing and Medicine House. A naming ceremony is still being planned with the province.
The province, through Northern Health, and the regional hospital district share the cost of the project.
The hospital board meets at 10 a.m. Thursday, Nov. 12, at the Peace River Regional District office, 1981 Alaska Avenue in Dawson Creek. The meeting streams on the PRRD's Facebook page.
Sources: PRRHD board agenda package, Nov. 12, 2026 (Northern Health 2026-27 Capital Plan Update and Facility Condition Index, Oct. 5), PRRD notice of meeting, Northern Health project page, Northern Health, April 2026 update, Northern Health, patient move FAQ, Northern Health, old hospital FAQ, Energeticcity (Feb. 26, 2026), CBC News (April 20, 2026), My Peace Region Now (Aug. 5, 2026)..
You may like
Twelve more First Nations buy into Coastal GasLink, the pipeline that starts near Dawson Creek
School District 60 cancels buses as freezing rain glazes Peace roads, but schools stay open
Indigenous businessman says repealing B.C.'s DRIPA law would not strip First Nations of their rights, as other leaders warn of conflict