Dawson Creek's water decision lands on a new council, with four options priced from $55 million to $272 million

No source has been picked. Mayor Dwaine Dilworth says the city needs senior government and oilfield partners and a clear picture of annual operating costs.

Published Nov 8, 2026 in Dawson Creek
By The NEBC Current newsroom
The Kiskatinaw River beneath the Alaska Highway bridge in 2017
The Kiskatinaw River beneath the Alaska Highway bridge in 2017. File photo, not the water intake near Arras. Photo: Jason Woodhead via Wikimedia Commons, CC BY 2.0. Resized. Licence: https://creativecommons.org/licenses/by/2.0/

Update, Monday, Nov. 9: the City now says it may pull the project out of the provincial environmental assessment. Read more.

DAWSON CREEK, B.C. - The most expensive decision facing Dawson Creek's new council is still undecided, and the price tags are large.

A Phase 1 feasibility study presented to council at the Aug. 10 Committee of the Whole narrowed the city's long-term water options to four, according to the City. CBC News reported staff estimates for each. Staying on the Kiskatinaw River, the current source, would cost about $55 million to maintain existing infrastructure, plus drought and emergency planning, and $85 million if overland pumping is needed. Drawing from the Pine River is estimated at $194 million, the Peace River near Clayhurst at $255 million, and the Peace River near Taylor at $272 million. CBC reported the earlier estimate for a pipeline was around $100 million.

Over 50 years, maintenance costs were put at $236 million for the Pine River, $280 million for Clayhurst and $314 million for Taylor, CBC reported. The study named the Taylor and Clayhurst areas as the most resilient to climate change, CBC reported, citing the report. The City says the study identified no preferred option.

The pressure behind the work is real. The City says low flows in the Kiskatinaw prevented pumping for almost two months in early 2024. The river is the main source for Dawson Creek and Pouce Coupe, serving about 15,000 people, CBC reported. The City also says a temporary emergency overland transfer system is being prepared so it can be deployed quickly under a short-term approval from the province.

On Aug. 24 council approved Phase 2A, which covers engagement and project definition, along with partnership and funding work, My Peace Region Now reported. Energeticcity.ca reported the city said Phase 2B, with detailed technical, routing and environmental studies, will go ahead only if council decides so after the 2A results.

The Taylor and Clayhurst routes are tangled up with another Peace River question. City staff told CBC that BC Hydro's proposed Site E dam, which it is studying, would flood parts of both areas. Coun. Jerimy Earl said it would be prudent to start talking with BC Hydro early in case the city could save money by lining up with that corridor.

Dilworth, who was sworn in as mayor Nov. 2, told CJDC-TV after his election that pipe in the ground is a one-time cost but operating costs come every year, and "we really need to know that." He said the project cannot be done by the city alone. "The only way we're going to be able to make it happen is to get some government involvement, oil field involvement, Dawson Creek involvement, and work together to get it done," he said.

The City says the project aims to serve domestic use, agriculture, industry and wildfire mitigation for Dawson Creek, Pouce Coupe and the surrounding area. As of Aug. 31 the city said no preferred source or route has been chosen. Details and a feedback form are on the City's Water Supply System Project page, or at [email protected].

We're still keeping an eye out for more on this story and will update it if anything changes.

Sources: City of Dawson Creek, Water Supply System Project page (Phase 1 results and background). CBC News, "Dawson Creek water pipeline could cost up to $272M to build, new estimates show" (Tom Summer, Aug. 12, 2026). My Peace Region Now, "Dawson Creek moves ahead with next phase of long-term water supply planning" (Celestia Nlemvo, Sept. 1, 2026). Energeticcity.ca, "Dawson Creek Water Supply project moves to phase two" (Ethan Van Dop, Sept. 1, 2026). CJDC-TV, "Dwaine Dilworth elected mayor of Dawson Creek" (Oct. 18, 2026)..