Local
Charlie Lake sewer engineering contract would reach $1.16 million under a change back before the regional board Thursday
Directors put off the amendment in August. It returns after a budget meeting with the Area C director.
By The NEBC Current newsroom
CHARLIE LAKE, B.C. - The Peace River Regional District's engineering contract for the Charlie Lake sewer system would grow to about $1.16 million if directors approve a change on Thursday's board agenda.
Staff want the board to add $295,080 to the deal with McElhanney Ltd. and stretch it one more year, to Dec. 31, 2027. The contract began at $750,000 after a 2022 request for proposals. Last November the board lifted it to $860,000 to pay for design work on the east side of the lake.
This is not the first time the amendment has come up. Directors deferred it on Aug. 13 to a draft budget meeting between the Electoral Area C director and staff, the agenda notes, and it is now back for a decision. Energeticcity reported on the proposal in August.
By a July 7 project meeting, about $771,183 of the current $860,000 had been spent, leaving close to $88,817, according to the staff report. Staff say that covers the rest of this year's planned work, including flow monitoring stations and valve replacements.
Most of the new money, about $245,400, would pay for design, tendering and contract administration on 2027 capital projects. Another $31,680 is for management and administration and $18,000 is for other engineering help. The report draws on Peace River Agreement money and gas tax funds, and marks the capital piece as a supplemental budget request.
Staff say keeping the same firm holds on to technical knowledge while development keeps pushing on the system. The report says most of the Charlie Lake capital improvement plan was finished between 2023 and 2026, from lagoon dredging and lift station upgrades to backup power and new backup piping along Lakeshore Drive and the Alaska Highway. Next on the list for the 2027 and 2028 budgets are High-Level Crescent and backup piping on Beach Street and Charlie Lake Crescent.
Some of this year's work is already underway. The regional district said in October that Big League Utilities Ltd. would repair and replace sewer pipe from Oct. 21 until the end of December, working between 8 a.m. and 5 p.m., with restoration and hydroseeding next spring.
The bigger bills are still ahead. McElhanney's east side plan from last year put a new regional lift station at roughly $1.38 million and twinning about two kilometres of sewer main at roughly $1.03 million, figures Energeticcity also reported in October 2025.
The board meets Thursday at 10 a.m. at the regional district office in Dawson Creek.
Sources: Peace River Regional District, report ENV-BRD-289 "Contract Amendment - RFP 54-2022 Engineering Services for Charlie Lake Sewer" and Nov. 12, 2026 board agenda. PRRD, "Charlie Lake Sewer - East Side Capital Improvement Plan" (2025). PRRD notice, "Construction Notice for Charlie Lake Residents: Sanitary Sewer Upgrades" (Oct. 19, 2026). Energeticcity.ca, "PRRD to amend Charlie Lake sewer system engineering contract" (Aug. 14, 2026) and "PRRD approves 2027 upgrades work on Charlie Lake sewer" (Oct. 6, 2025)..
You may like
December is one of the most dangerous months on B.C. roads, and safety groups are urging drivers to slow down and plan ahead
Company behind a 30-turbine wind farm south of Fort St. John asks the regional district to rezone farmland, and directors push back
Former premier David Eby skips the NDP swearing-in as his shrunken caucus takes its seats in Opposition
Twelve more First Nations buy into Coastal GasLink, the pipeline that starts near Dawson Creek
School District 60 cancels buses as freezing rain glazes Peace roads, but schools stay open